Paving Work Updates

Continue to check this page for updates about the paving portion of the project

 

WHAT TO EXPECT – PAVING

November 6, 2026:  All work has been completed!!!  The roadways will be reopened around 5:00pm. Thank you to all the residents for your patience and all the volunteers that helped with this project!!!

UPDATES:

Update 10/26/2026 - Camella Lane completed and reopened for vehicles.

Update 10/27/2026 - Due to mechanical concerns, only Cypress Crossing was completed today.  The schedule for the rest of this week has been updated.  The updated dates for the work are listed below. 

Update 10/28/2026 - Hampton Glen Dr. completed and reopened for vehicles.

Update 10/29/2026 - Hampton Glen Dr. completed and reopened for vehicles at 6:00pm.  Ash Grove Lane partially completed and open for vehicle traffic at 6:00pm.  Ash Grove will be completed tomorrow, Friday October 30, 2026.  

Update 10/30/2026 - Ash Grove and Ryman completed and reopened.  Lomond Lane partially completed. The remainder of Lomond Lane will be completed on Monday November 2, 2026.

Update 11/02/2026 - Due to inclement weather, no paving work will be completed on Monday November 2, 2026.  The work will begin again tomorrow on 11/3/2026.  The updated schedule is below.  Please note that the schedule may continue to change with other weather delays, or updates to the construction schedule.  

Update 11/03/2026 - Everything completed as scheduled!  Lomond Lane and the portion of Dunham Station completed are reopened!

Update 11/04/2026 - Everything completed as scheduled!  Ryman Place, Oak Alley and the portion of Dunham Station completed are reopened!

Update 11/05/2026 - Due to mechanical concerns at the asphalt plant, the full work was not able to be completed today. We are confident that this will not delay us from finishing tomorrow.  Tomorrow (11/06/2026), the crew will complete the remaining section from today's work and then will complete the scheduled areas for tomorrow.  

 

IMPORTANT:

    • Please be aware of the crew and where they are working. Adhere to the direction of the flag men.
    • To avoid dust collection or damage to your vehicle, we strongly recommend that you park in a NON-WORK zone for that day, in your garage, or off property.
    • To avoid dust in the home, keep all windows closed during the paving project.
    • DO NOT park any vehicle in the drive lanes or work zones as they will be towed at the owner’s expense.
    • DO NOT allow pets to walk on new pavement when crews are still in place. Asphalt is installed at 300 degrees Fahrenheit and will burn the pads of their paws.
    • DO NOT utilize any type of wheeled device on new pavement for 24 hours to avoid damage to the wheels or tires.
    • DO NOT let children walk, ride or cross over the new pavement if the roadways are still closed. The asphalt is extremely hot and will stick to their shoes.
    • Inform personal guests, nurses, home health care aides, service people etc. so that they are aware of the paving schedule as well.
    • Reschedule any vendor services that are scheduled to complete service on the same day that paving is being completed on your street.  REMEMBER THAT NO VEHICLES, INCLUDING VENDOR VEHICLES, WILL BE PERMITTED TO ACCESS THE ROADWAYS WHILE THE ASPHALT IS COOLING!
    • All irrigation must be turned off for the entirety of the project.
    • Residents may notice sand being applied to the new asphalt as sections are completed. This is a normal and important part of the paving process. The sand helps to prevent equipment and work boots from sticking to the fresh asphalt and it helps protect the surface from spalling and pocking when vehicles drive on the new asphalt.  The sand will remain on the roadway after reopening. It will naturally break down, wash into the pavement with rainfall, and dissipate over time.

ROADWAY CLOSURES:

While the paving work is ongoing and while the new pavement is curing and cooling, the roadway will be closed to all vehicle traffic!  There are no exceptions to this!  No vehicles will be permitted on any newly paved roadway until it is deemed safe to do so by our vendor and consultant. It can take up to four (4) hours after paving is completed for the surface to cool enough for vehicles to safely drive on it. This means the roadway will be closed for the majority of the day.

Residents are advised to plan ahead and move any vehicles that will be needed that day to an approved parking location outside of the work zone before work begins.

If you need to use your vehicle on the day your roadway is being paved, please move it to an approved parking location off the roadway by 7:00 a.m. on the day the work is scheduled.

Residents must ensure they reschedule any deliveries, vendors, guests or other visitors the day(s) their roadway will be closed. Any delivery, guest, vendors or other vehicles will be turned away and stopped from entering the roadway!

Any vehicle parked in your driveway or garage during the paving work will not be able to leave until the roadway is reopened. Please plan ahead, as the roadway will remain closed for most of the day while work is in progress.

Any vehicle left on the roadway during the paving project will be towed at the vehicle owner's expense.  No exceptions!

Details about the approved parking areas are provided at https://www.egrandhampton.com/vehicle-parking-updates/

Projected Work Schedule:

NOTE:  These dates are subject to change due to weather or other unforeseen delays.  We will update the webpage and notify the residents as soon as possible if there are changes to the projected schedule.

October 26, 2026:

Camella Lane

Paving Day 1 White 10-26-2026

October 27, 2026:

 Cypress Crossing Ct.

Paving Day 2 Green 10-27-2026

October 28, 2026:

Hampton Glen Dr.

Paving Day 2 Green 10-27-2026

October 29, 2026:

Ash Grove Lane and Chestnut Grove Dr.

Paving Day 3 Purple 10-28-2026

October 30, 2026:

Complete Ash Grove Lane, then Lomond Lane and Ryman Place. 

Paving Day 4 Red 10-29-2026

November 3, 2026:

Finish Lomond Lane and Dunham Station Dr. partial (Addresses 8439 - 8492). 

Paving Day 5 Blue 11-2-2026

November 4, 2026:

Oak Alley Dr. and Dunham Station Dr. partial (Addresses 8419 - 8437)

NOTE:  Residents living on Ryman Place will not be able to access their roadway while this section of Dunham Station is being completed.  

Paving UPDATE 11-03-2026

November 5, 2026:

Dunham Station Dr. partial (Addresses 8356 - 8419)

NOTE:  Residents living on Cane River Way, Fair Hill Way, Pergola Bend, Pond Spring Way, Shady Hill Lane, and Windsor Bluff Dr. will not be able to access their roadway while this section of Dunham Station is being completed.  

Paving UPDATE 11-04-2026

November 6, 2026: 8354 Dunham Station north until the roundabout.

IMPORTANT: This work will prevent vehicle access to and from the entire east side of the community for the majority of the day. This closure will affect ALL residents on the following roadways: Dunham Station Drive (east side, all addresses between 8343 and 8492), Cane River Drive, Club Vista Lane, Fair Hill Way, Lomond Lane, Manor Club Circle, Moss Hill Lane, Oak Alley Drive, Old Town Drive, Pergola Bend, Pond Spring Way, Ryman Place, Shady Hill Lane, Walnut Grove Drive and Windsor Bluff Drive.

Paving UPDATE 11-06-2026