Milling Work Updates

Continue to check this page for updates about the milling portion of the project

UPDATES:

UPDATE 10/12/26 - Camella Lane milling completed on schedule.  

UPDATE 10/13/26 - Hampton Glen and Cypress Crossing milling completed on schedule.  

UPDATE 10/14/26 - Ash Grove Lane and Chestnut Grove milling completed on schedule.  

UPDATE 10/19/26 - Dunham Station partial (addresses 8439 - 8477) milling completed on scheduled  

UPDATE 10/20/26 - Oak Alley Drive milling completed on schedule.  

UPDATE 10/21/26 - Small area between 8415 Dunham Station and 8423 Dunham Station unfinished.  This area will be completed on 10/22/26 along with the rest of the work scheduled for 10/22/2026.  

UPDATE 10/22/26 - All milling work has been completed.  Paving will start on Monday, October 26, 2026.  The details about the paving project can be found at https://www.egrandhampton.com/paving-work-updates/.   

WHAT TO EXPECT – MILLING

 IMPORTANT:

  • DO NOT attempt to pass under or drive under the boom lift of the milling machine when in operation. Do not assume that the truck drivers or equipment operators can see or hear you as they are watching the operator for hand signals.
  • Please be aware of the crew and where they are working.  Adhere to the direction of the flag men.
  • To avoid dust collection on your vehicle, we strongly recommend that you park in a NON-WORK zone for that day, in your garage, or off property.
  • To avoid dust in the home, keep all windows closed during the milling and paving project.
  • DO NOT park any vehicle in the designated work areas as they will be towed at the owner’s expense.
  • Inform personal guests, nurses, home health care aides, service people etc. so that they are aware of the milling schedule as well.
  • All irrigation must be turned off for the entirety of the project.

Projected Work Schedule:

NOTE:  These dates are subject to change due to weather or other unforeseen delays.  We will update the webpage and notify the residents as soon as possible if there are changes to the projected schedule.

October 12, 2026:

Camella Lane

Milling Day 1 White 10-12-2026

October 13, 2026:

Hampton Glen Dr. and Cypress Crossing Ct.

Milling Day 2 Green 10-13-20206

October 14, 2026:

Ash Grove Lane and Chestnut Grove Dr.

Milling Day 3 Purple 10-14-2026

 October 15, 2026:

Lomond Lane, Ryman Place, and Dunham Station Dr. partial (Addresses 8429 - 8437)

Milling Day 4 Red 10-15-2026

October 19, 2026:

Dunham Station Dr. partial (Addresses 8439 - 8477)

Milling Day 5 Blue 10-19-2026

October 20, 2026:

Oak Alley Dr.

Milling Day 6 10-20-2026

October 21, 2026:

Dunham Station Dr. partial (Addresses 8356 - 8434)

Milling Day 7 10-21-2026

October 22, 2026:

Dunham Station Dr. partial (Addresses 8354 north until the roundabout)

Milling Day 8 10-22-2026